RCP joined after the construction contract had been procured, as project manager and Engineer's Representative, and steadied a project that had struck early difficulty. Through Covid-era cost pressure, RCP managed the NZS 3916 design-and-build contract, keeping variations justified and tied to the agreed scope. When the façade subcontractor went into liquidation with around 80 percent of its work done, RCP worked with the client and the liquidator to protect the University's position, brought in a replacement and kept construction on track.
Te Rangihīroa College opened in 2023 and took its first full cohort of 450 students in 2024, earning a 6 Green Star Design and As-Built rating, one of the greenest student residences in the country.