RCP was project manager and Engineer to the Contract, running the consultant team and main contractor from design through to completion and coordinating the base build with Auckland Council's integrated fit-out. As supply chains seized, RCP worked with the client and contractor to resequence the programme, fix pricing progressively, procure long-lead items early and source alternative and local materials, checking each option against the building's Green Star targets.
When sheet-pile availability threatened the programme, RCP supported the contractor's call to flip the basement construction sequence to keep the job moving, and Auckland Council's contractor was given early access to work in parallel so the integrated fit-out held its dates.
Completed in July 2023, 6-8 Munroe Lane gave Auckland Council its consolidated northern home and the North Shore a green A-grade office. The building is fully electric with no gas, holds a 5 Green Star Design and As Built rating, and diverted almost 80 percent of its construction waste from landfill.
Awards
- 2024 Property Council New Zealand Property Industry Awards, Merit, Commercial Office
- 2024 Property Council New Zealand Property Industry Awards, Merit, Resene Sustainable Building
- 2024 Master Builders New Zealand Commercial Project Awards, Gold